Planning and Estimating is about 15% of the CSLB General Building (B) exam. CSLB's B study guide splits it into six subtopics: scope of work and code compliance, design and construction error identification, reading shop drawings, plans and specifications, field inspection performance, coordination of the project, and cost estimation for materials, equipment and labor. The rules come mostly from the administrative chapters of the 2025 California Residential Code (CRC) and California Building Code (CBC), with pieces of CALGreen, the Energy Code, the Plumbing Code and Cal/OSHA's Title 8. Estimating is arithmetic: CSLB provides a calculator, and its own sample question asks for the volume of a cylinder.
This note covers the numbers and rules each subtopic leans on, with the section each one comes from. The 2025 California codes took effect on January 1, 2026. The CRC renumbered much of Chapter 3 in 2025, so we give the new numbers: egress is R318, sprinklers R309, smoke alarms R310 and carbon monoxide alarms R311.
Scope of work and code compliance
Which code applies
- Title 24 parts. The CBC is Part 2, the CRC Part 2.5, the Energy Code Part 6, the Wildland-Urban Interface Code Part 7 and CALGreen Part 11. (Building Standards Commission)
- CRC scope. The CRC covers detached one- and two-family dwellings and townhouses not more than 3 stories above grade plane, each with its own means of egress, and their accessory structures. Other buildings fall under the CBC. (2025 CRC §R101.2)
Work that needs no permit
An exemption removes only the permit; the work must still meet the code. On a house lot, these need no building permit (2025 CRC §R105.2):
- A one-story detached shed or playhouse of 120 square feet or less.
- A fence 7 feet high or less.
- A retaining wall 4 feet high or less, measured from the bottom of the footing to the top of the wall, that holds no surcharge such as a driveway.
- Painting, papering, tiling, carpeting, cabinets, countertops and similar finish work.
- A prefabricated pool less than 24 inches deep, a window awning projecting 54 inches or less, and a water tank on grade of 5,000 gallons or less.
- A deck only when all four conditions hold: 200 square feet or less, no more than 30 inches above grade at any point, not attached to the dwelling, and not serving the required exit door.
A 160-square-foot deck 20 inches high that is attached to the house needs a permit: it fails the third condition. Under the CBC, a fence that serves as a pool barrier needs a permit at any height (2025 CBC §105.2).
Permit time limits
| Clock | Limit | Source |
|---|---|---|
| Application not pursued | Abandoned 180 days after filing | 2025 CRC §R105.3.2 |
| Issued permit, work not started | Invalid after 12 months | 2025 CRC §R105.5.1 |
| Work suspended or abandoned | Invalid after 12 months | 2025 CRC §R105.5.1 |
| Each extension of a permit | Not more than 180 days, on written request | 2025 CRC §R105.5.1 |
The 12-month rule in R105.5.1 governs permits issued on or after January 1, 2019; the 180-day figure printed in R105.5 does not. (2025 CRC §R105.5.1) Keep the permit, or a copy, on the job until the project is done (2025 CRC §R105.7). No one may occupy a building until the building official issues a certificate of occupancy; passing the final inspection is not enough by itself (2025 CBC §111.1).
Rules the scope can trigger
- Fire sprinklers. Every new one- and two-family dwelling needs them, with no size trigger. An addition or alteration to an existing unsprinklered house does not. An ADU is exempt only when all four conditions hold: it meets the Government Code definition of an ADU, it is detached and 1,200 square feet or less, it is on the same lot as the main house, and the main house has no sprinklers. (2025 CRC §R309.2)
- Smoke alarms. A permitted alteration, repair or addition brings the whole dwelling up to new-home smoke alarm locations. (2025 CRC §R310)
- Unit separations. Two-family dwelling: 1 hour, or 1/2 hour if sprinklered throughout (2025 CRC §R302.3.2). Townhouse common wall: 1 hour with sprinklers, 2 hours without (2025 CRC §R302.2.2).
- Address numbers. At least 4 inches high with a 1/2-inch stroke, visible from the street. (2025 CRC §R308.1)
- Flood areas. The lowest floor is at least the base flood elevation plus 1 foot, or the design flood elevation if higher. (2025 CRC §R306.2.1)
- Accessibility. Buildings with 3 or more dwelling units, or 4 or more condominium units, follow CBC Chapter 11A (2025 CRC §R322.1). Under Chapter 11B, an accessible ramp is no steeper than 1:12, rises no more than 30 inches per run and has landings at least 60 inches long (2025 CBC §11B-405).
- Energy and green code. A new home needs PV under the prescriptive standards unless the solar access roof area is under 80 contiguous square feet or the required system is under 1.8 kWdc (2025 Energy Code §150.1(c)14). CALGreen Chapter 4 reaches an existing home only where the work adds conditioned area, volume or size, and only in that area (2025 CALGreen §301.1.1).
Design and construction error identification
A design error is on the drawings; a construction error is in the field. Passing an inspection does not make a violation legal: the contractor still corrects it. CSLB's sample question here marks inadequate soil preparation as the most likely cause of a severe foundation crack.
Framing cuts
| Cut in a sawn joist, rafter or beam | Limit | Source |
|---|---|---|
| Notch depth, away from the ends | 1/6 of the depth | 2025 CRC §R502.8.1 |
| Notch length | 1/3 of the depth | 2025 CRC §R502.8.1 |
| Notch at the ends | 1/4 of the depth | 2025 CRC §R502.8.1 |
| Notch in the middle third of the span | Never | 2025 CRC §R502.8.1 |
| Bored hole diameter | 1/3 of the depth, edge 2 inches from top, bottom, other holes and notches | 2025 CRC §R502.8.1 |
Engineered lumber and trusses follow the manufacturer or a registered design professional, not these fractions. No truss member, including a web, may be cut without the design professional's approval. (2025 CRC §R502.8.2, §R502.12.3)
Foundations, walls and rooms
- Foundation walls must be engineered when they hold more than 48 inches of unbalanced backfill without lateral support, or face hydrostatic pressure. (2025 CRC §R404.1.1)
- Presumptive soil bearing (no soils report): crystalline bedrock 12,000 psf, sedimentary rock 4,000, sandy gravel 3,000, sand and silty sand 2,000, clay and silt 1,500 psf. A 2-foot-wide footing on sandy gravel carries 3,000 × 2 = 6,000 pounds per linear foot. (2025 CBC §1806.2)
- Exterior walls near a lot line, unsprinklered house: a wall closer than 5 feet is 1-hour rated from both sides; no openings under 3 feet, 25% of the wall at 3 feet, unlimited at 5 feet; no eaves within 2 feet. (2025 CRC §R302.1)
- Garage door to the house: 1 3/8-inch solid wood or steel, or 20-minute rated, self-closing and self-latching; never into a sleeping room (2025 CRC §R302.5.1). Garage separation is 1/2-inch gypsum on the garage side, 5/8-inch Type X when living space is above (2025 CRC §R302.6).
- Ceiling height. Habitable rooms and hallways need 7 feet; bathrooms and laundry rooms 6 feet 8 inches. (2025 CRC §R313.1)
- Egress door. At least 32 inches clear width and 78 inches clear height, side-hinged, with no path through a garage. A ramp to it is no steeper than 1 in 12. (2025 CRC §R318.2, §R318.8)
- Smoke alarms go in each sleeping room, outside each sleeping area and on each story, at least 3 feet from a bathroom door with a tub or shower and normally 20 feet from a cooking appliance. (2025 CRC §R310.3)
- Carbon monoxide alarms are needed in a dwelling with a fuel-burning appliance or fireplace, or an attached garage with an opening into the home. They go outside each sleeping area and on every occupiable level, and must be interconnected when more than one is needed. (2025 CRC §R311.3, §R311.5)
- Flood openings: 1 square inch per square foot of enclosed area, at least two on different sides, bottom no more than 1 foot above grade. A 1,200-square-foot crawl space needs 1,200 square inches. (2025 CRC §R306.2.2)
- Grab bar backing in a new home: at least 2x8, between 32 and 39 1/4 inches above the floor (2025 CRC §R328.1.1).
Shop drawings, plans and specifications
- Plan views. A site plan looks down on the lot, a floor plan is a horizontal cut, an elevation shows an outside face, and a section is a vertical cut through the building. The site plan shows distances from lot lines and existing and finished grades. (2025 CBC §107.2.6)
- Shop drawings show exactly how an item will be made and installed. In common building practice the fabricator or subcontractor prepares them, and they go through the contractor to the design professional for review before the item is made. The CBC requires fire protection shop drawings to be approved before installation starts. (2025 CBC §107.2.2)
- Submittal. Construction documents go in with the permit application in two or more sets, or digitally where allowed (2025 CBC §107.1). The building official keeps one approved set, and the other is kept at the work site (2025 CBC §107.3.1; 2025 CRC §R106.3.1). A field change is resubmitted as amended documents (2025 CBC §107.4). The official keeps approved documents at least 180 days after completion (2025 CBC §107.5).
- Deferred submittals need the building official's prior approval, and the item may not be installed until its documents are approved. (2025 CBC §107.3.4.1)
- Trusses. Roof truss design drawings are approved before the trusses are installed, and a set comes with the shipment. (2025 CRC §R802.10.1)
- Stamped design. In California, prescriptive masonry walls still need documents stamped by a licensed architect or engineer, despite the section's heading. (2025 CRC §R606.1.1) A shoring system that protects adjacent property is designed by a registered design professional (2025 CBC §3307.2.1).
Reading scale. At 1/4 inch = 1 foot, 1 inch on the drawing is 4 feet; at 1/8 inch = 1 foot, it is 8 feet. A building 5 by 3 1/2 inches on a 1/8-inch plan is 40 by 28 feet, so 1,120 square feet. Convert each side first, then multiply.
Room layout checks (2025 CRC §R312.1, §R312.2; 2025 CRC §R318.6; 2025 CRC §R325.1.1):
- A habitable room has at least 70 square feet and is at least 7 feet in every direction (kitchens excepted). A 6-by-12-foot room has 72 square feet but fails.
- A hallway is at least 3 feet wide.
- Natural light glazing is at least 8% of the floor area.
- Joists for sleeping rooms use the 30 psf live load table; other rooms use 40 psf (2025 CRC §R502.3.1).
Field inspection performance
Work stays visible until it is approved, and the permit holder calls for each inspection. The order matters (2025 CRC §R109.1; 2025 CBC §110.3):
| Inspection | When | Source |
|---|---|---|
| Foundation | Trenches dug, forms set, rebar in place; before concrete | 2025 CRC §R109.1.1 |
| Slab and under-floor | Piping, conduit and rebar in place; before concrete or subfloor | 2025 CRC §R109.1.1.1 |
| Rough plumbing, mechanical, gas, electrical | Before cover and before the frame inspection | 2025 CRC §R109.1.2 |
| Frame | Roof, framing, fireblocking, bracing in place; rough systems approved | 2025 CRC §R109.1.4 |
| Lath and gypsum board | Board up; before plaster or taping | 2025 CRC §R109.1.4.2 |
| Final | Work complete; before occupancy | 2025 CRC §R109.1.6 |
- Framing moisture. Framing may not be enclosed above 19% moisture content; take readings 2 to 4 feet from the grade-stamped end, at least 3 random readings. (2025 CALGreen §4.505.3)
- Fireblocking in stud walls at floor and ceiling and every 10 feet horizontally, with 2-inch nominal lumber, 23/32-inch panel or 1/2-inch gypsum among the accepted materials (2025 CRC §R302.11). Draftstops divide floor-ceiling spaces into areas of no more than 1,000 square feet (2025 CRC §R302.12).
- Duct leakage, new home: no more than 5% of air handler airflow, or 4% at rough-in without the air handler. (2025 Energy Code §150.0(m)11)
- Plumbing tests. DWV water test with at least a 10-foot head for 15 minutes; DWV air test 5 psi (2025 CPC §712.2, §712.3). Water supply: working pressure with water, or 50 psi air, never air on plastic except PEX, PP or PE-RT where allowed (2025 CPC §609.4). Gas piping: 10 psi for 15 minutes (2025 CPC §1213.3).
- Crawl space access: 18 by 24 inches through the floor, 16 by 24 inches through a wall. (2025 CRC §R408.4)
- Your own survey. Before employees are on the site, the employer surveys it for predictable hazards. (8 CCR §1511)
Coordination of project
- Call 811. Notify the regional notification center, and known owners who are not members, at least 2 working days before digging. Digging starts only after the area is marked and every known owner has given a positive response. Within 10 feet of a high-priority line, such as gas over 60 psig, meet the owner on site first. (8 CCR §1541)
- Neighbors. Give adjacent owners written notice at least 10 days before excavation. (2025 CBC §3307.1)
- Pedestrians. Construction 8 feet high or less within 5 feet of the lot line needs construction railings at least 42 inches high; taller work close to the lot line needs a barrier and covered walkway. A walkway is at least 4 feet wide; a barrier at least 8 feet high. Materials stay at least 20 feet from a street intersection. (2025 CBC §3306, §3308.1.1)
- Demolition. Pedestrian protection goes up first (2025 CBC §3303.2). Utilities are shut off or capped, a written survey of the structure is made, and walls and floors come down from the top, one story at a time (8 CCR §1735). The federal asbestos rule needs written notice at least 10 working days before demolition of a covered facility, which leaves out residential buildings of 4 or fewer units (40 CFR §61.145).
- Fire safety. Above 40 feet over fire department access, a stairway is required and kept within one floor of the top decked level. (2025 CBC §3310.1)
- Waste. Recycle or salvage at least 65% of nonhazardous construction and demolition waste. A waste plan measures diversion by weight or volume, not both. (2025 CALGreen §4.408)
- Closeout. An operation and maintenance manual is placed in a new home at the final inspection, including guidance on keeping indoor humidity at 30 to 60%. (2025 CALGreen §4.410.1)
Cost estimation for materials, equipment, and labor
These are common building practice and plain arithmetic, not code rules. Write the unit on every number, add waste by multiplying by (1 + rate), and round up to whole purchase units.
| Unit or formula | Value |
|---|---|
| Cubic yard | 27 cubic feet |
| Square yard | 9 square feet |
| Roofing square | 100 square feet |
| 4x8 sheet | 32 square feet |
| Board feet | thickness (in) × width (in) × length (ft) ÷ 12 |
| Cylinder volume | 3.14 × radius × radius × length |
Worked examples
- CSLB's cylinder. 3 feet in diameter, 12 feet long: 3.14 × 1.5 × 1.5 × 12 = 84.78 cubic feet.
- Slab. 30 by 18 feet, 6 inches thick: 30 × 18 × 0.5 = 270 cubic feet ÷ 27 = 10 cubic yards. Change inches to feet first.
- Studs. A 40-foot wall at 16 inches on center: 480 ÷ 16 = 30 spaces, plus 1 = 31 studs.
- Lumber. Fifty 2x6s, 12 feet long: 50 × 12 board feet = 600 board feet; at $1,200 per MBF, $720.
- Shingles. 1,800 square feet plus 10% waste = 19.8 squares; at 3 bundles a square, 59.4, so 60 bundles.
- Swell. 80 bank cubic yards with 25% swell = 100 loose cubic yards; to go back, divide by 1.25, do not subtract 25%.
- Labor. Three carpenters, 8 hours a day for 5 days, at $48 an hour: 120 hours × $48 = $5,760. With time and a half over 8 hours, a $40 carpenter working 10 hours earns $440.
- Equipment. A $60,000 skid steer sold for $10,000 after 5,000 hours costs $10 an hour (straight-line).
- Markup and margin. A 15% markup on $40,000 gives $46,000. A 25% margin on $60,000 cost is $60,000 ÷ 0.75 = $80,000.
Traps to watch for
- 180 days or 12 months? An unpursued application dies at 180 days and an extension is up to 180 days, but an issued permit lasts until 12 months pass without work.
- Old numbers. Egress, hallways and stairs moved to R318 in the 2025 CRC; R311 is now carbon monoxide alarms. A book citing older numbers is out of date.
- Order of inspections. Rough plumbing, electrical and mechanical are approved before the frame inspection; insulation and drywall come after it.
- Three air tests. DWV 5 psi, water supply 50 psi, gas 10 psi.
- Markup is not margin. Divide by (1 − margin) to reach a target margin; multiplying by (1 + markup) gives less profit than it seems.
- Round up. You cannot buy 59.4 bundles or 19.8 squares.
For answered practice questions on this section, start with scope and code compliance, design and construction errors, plans and specifications, field inspections, project coordination and cost estimation. For how this section fits the whole exam, see what's on the B exam.