Skip to content
CalContractorPrep
Menu

CSLB General Building (B) practice questions: Coordination of project

Section 1 of 5: Planning and Estimating

4 free practice questions on coordination of project, part of a section that is about 15% of the General Building exam. Try each one, then open the answer: every choice is explained, and the answer names the code section or public rule it comes from.

Questions and answers

  1. 1. A contractor will demolish a building that sits next to a public sidewalk. Under the California Building Code, when may the demolition begin?

    Planning and Estimating

    • A. Only after the required pedestrian protection is in place
    • B. Once warning signs are posted on the sidewalk, with barriers added later as needed
    • C. Right away, as long as a flagger watches the sidewalk
    • D. After the utilities are disconnected, whether or not pedestrian protection is in place
    Show answer

    Correct answer: A

    • A. Only after the required pedestrian protection is in place

      Correct answer

      Correct: the required pedestrian protection goes up before demolition starts (CBC 3303.2).

    • B. Once warning signs are posted on the sidewalk, with barriers added later as needed

      Wrong: signs are not the required protection, and it cannot be added after work starts.

    • C. Right away, as long as a flagger watches the sidewalk

      Wrong: a flagger does not replace the required pedestrian protection.

    • D. After the utilities are disconnected, whether or not pedestrian protection is in place

      Wrong: utilities must be disconnected too, but that does not replace the pedestrian protection.

    Explanation

    California Building Code section 3303.2 (Pedestrian protection) says demolition of a building may not begin until the required pedestrian protection is in place. The kind of protection (railings, a barrier, or a barrier and a covered walkway) is set by Section 3306. The protection comes first; signs, a flagger or disconnected utilities do not take its place.

  2. 2. A contractor will demolish an old commercial building. Under the California Building Code, what must be done with the building's service utility connections?

    Planning and Estimating

    • A. They may stay live so the crew has power and water during demolition
    • B. They must be disconnected and capped following the approved rules and the requirements of the governing authority
    • C. They may be buried in place when the lot is filled
    • D. They are left for the next building's contractor to deal with
    Show answer

    Correct answer: B

    • A. They may stay live so the crew has power and water during demolition

      Wrong: service connections are disconnected and capped, not left live.

    • B. They must be disconnected and capped following the approved rules and the requirements of the governing authority

      Correct answer

      Correct: service utility connections are disconnected and capped under the approved rules and the governing authority's requirements (CBC 3303.6).

    • C. They may be buried in place when the lot is filled

      Wrong: filling the lot does not take the place of disconnecting and capping the services.

    • D. They are left for the next building's contractor to deal with

      Wrong: the demolition work itself must disconnect and cap the services.

    Explanation

    California Building Code section 3303.6 (Utility connections) requires service utility connections to be disconnected and capped, following the approved rules and whatever the governing authority, such as the serving utility, requires. Other demolition rules in Section 3303: required pedestrian protection must be in place before demolition starts (3303.2), and a lot left vacant must be filled and kept at the existing grade or as local ordinance requires (3303.4).

  3. 3. On a new home, when must the CALGreen operation and maintenance manual be placed in the building?

    Planning and Estimating

    • A. When the building permit is issued
    • B. At the frame inspection
    • C. At the final inspection
    • D. Within 30 days after the owner moves in
    Show answer

    Correct answer: C

    • A. When the building permit is issued

      Wrong: the manual covers the finished building and is delivered at the end.

    • B. At the frame inspection

      Wrong: too early; the equipment is not yet installed.

    • C. At the final inspection

      Correct answer

      Correct: at final inspection (CALGreen 4.410.1).

    • D. Within 30 days after the owner moves in

      Wrong: it must be in the building at final inspection, not after occupancy.

    Explanation

    CALGreen section 4.410.1 requires an operation and maintenance manual (or accepted media such as a web-based reference) to be placed in the building at the time of final inspection. It covers items such as equipment and appliances, roof and yard drainage, space-conditioning systems and irrigation, and says it stays with the building.

  4. 4. A builder is putting together the CALGreen operation and maintenance manual for a new home. The manual must include educational material on keeping indoor relative humidity in what range?

    Planning and Estimating

    • A. 30 to 60 percent
    • B. 40 to 70 percent
    • C. 50 to 80 percent
    • D. 60 to 90 percent
    Show answer

    Correct answer: A

    • A. 30 to 60 percent

      Correct answer

      Correct: the manual explains keeping indoor relative humidity between 30 and 60 percent (4.410.1).

    • B. 40 to 70 percent

      Wrong: the range in 4.410.1 is 30 to 60 percent.

    • C. 50 to 80 percent

      Wrong: the range in 4.410.1 is 30 to 60 percent.

    • D. 60 to 90 percent

      Wrong: the range in 4.410.1 is 30 to 60 percent.

    Explanation

    CALGreen section 4.410.1 (Operation and maintenance manual) requires a manual, placed in the building at final inspection, that covers among other things the operation and maintenance of equipment, roof and yard drainage, space conditioning and irrigation, a direction that it stay with the building for the life of the structure, and educational material on keeping interior relative humidity between 30 and 60 percent.

Keep studying

Read the Section 1 study notes: Planning and Estimating

All General Building topics

Test yourself

Try 25 free General Building practice questions from all five sections. Each answer explains the rule and names the code section it comes from. No sign-up.

See what the General Building exam covers