Skip to content
CalContractorPrep
Menu

CSLB General Building (B) practice questions: Field inspection performance

Section 1 of 5: Planning and Estimating

4 free practice questions on field inspection performance, part of a section that is about 15% of the General Building exam. Try each one, then open the answer: every choice is explained, and the answer names the code section or public rule it comes from.

Questions and answers

  1. 1. On a new raised-floor house, the inspector looks into the crawl space and finds grass, weeds and roots on the ground. Under the California Residential Code, what is required for the under-floor grade?

    Planning and Estimating

    • A. It must be cleaned of all vegetation and organic material
    • B. The vegetation may stay if a vapor retarder is laid over it
    • C. The vegetation may stay if the crawl space is vented
    • D. Only vegetation within 18 inches of the floor joists must be removed
    Show answer

    Correct answer: A

    • A. It must be cleaned of all vegetation and organic material

      Correct answer

      Correct: all vegetation and organic material comes out of the under-floor grade (R408.5).

    • B. The vegetation may stay if a vapor retarder is laid over it

      Wrong: a vapor retarder does not replace removing the vegetation.

    • C. The vegetation may stay if the crawl space is vented

      Wrong: venting the crawl space does not replace removing the vegetation.

    • D. Only vegetation within 18 inches of the floor joists must be removed

      Wrong: 18 inches is the R304.1 distance from exposed ground inside which floor joists must be naturally durable or preservative-treated wood, not a vegetation rule; all vegetation must go.

    Explanation

    California Residential Code section R408.5 (Removal of debris) requires the under-floor grade to be cleaned of all vegetation and organic material. Covering it or venting the crawl space does not replace the cleaning, and there is no height allowance for vegetation left in place.

  2. 2. The ducts in a new single-family house are leak tested at rough-in, before the air handler is installed. Under the California Energy Code, total duct leakage may not exceed what share of the air handler airflow?

    Planning and Estimating

    • A. 3 percent
    • B. 4 percent
    • C. 5 percent
    • D. 8 percent
    Show answer

    Correct answer: B

    • A. 3 percent

      Wrong: tighter than the code requires.

    • B. 4 percent

      Correct answer

      Correct: 4 percent at rough-in when the air handler is not yet installed (CEnC 150.0(m)11).

    • C. 5 percent

      Wrong: 5 percent is the limit when the air handler is installed and connected.

    • D. 8 percent

      Wrong: more leakage than the code allows.

    Explanation

    California Energy Code section 150.0(m)11 requires forced-air duct systems to be sealed and confirmed by field verification and diagnostic testing. For single-family dwellings and townhouses tested at rough-in with the air handler not yet installed, total leakage may not exceed 4 percent of the air handler airflow. With the air handler installed and connected, the limit is 5 percent.

  3. 3. The frame inspection on a house is scheduled for Thursday. The drywall crew is free on Wednesday. Under the California Residential Code, what should the contractor do?

    Planning and Estimating

    • A. Hang the drywall Wednesday; the inspector can check the framing from the attic
    • B. Hang drywall on one side of each wall only
    • C. Wait until the frame inspection is approved before covering the framing
    • D. Hang the drywall and keep photos of the framing for the inspector
    Show answer

    Correct answer: C

    • A. Hang the drywall Wednesday; the inspector can check the framing from the attic

      Wrong: the framing must stay exposed until it is approved.

    • B. Hang drywall on one side of each wall only

      Wrong: covering any part of the framing goes past the inspection point.

    • C. Wait until the frame inspection is approved before covering the framing

      Correct answer

      Correct: no work beyond the inspection point until approval (R109.4).

    • D. Hang the drywall and keep photos of the framing for the inspector

      Wrong: photos do not replace the required approval.

    Explanation

    California Residential Code section R109.4 bars the contractor from carrying the work beyond each inspection point until the building official has signed off on it. Covering the framing before the frame inspection is approved goes past that point.

  4. 4. At the footing and foundation inspection for a commercial building, the foundation materials are supposed to be on the job. Which material does the California Building Code allow to be absent at the time of the inspection?

    Planning and Estimating

    • A. Reinforcing steel
    • B. Form lumber for the concrete foundation
    • C. Anchor bolts
    • D. Ready-mixed concrete
    Show answer

    Correct answer: D

    • A. Reinforcing steel

      Wrong: required reinforcing steel must already be in place for this inspection.

    • B. Form lumber for the concrete foundation

      Wrong: for concrete foundations the required forms must already be in place.

    • C. Anchor bolts

      Wrong: foundation materials must be on the job; only ready-mixed concrete is excepted.

    • D. Ready-mixed concrete

      Correct answer

      Correct: ready-mixed concrete is the stated exception (CBC 110.3.1).

    Explanation

    California Building Code section 110.3.1 makes the footing and foundation inspection after the excavations are complete and any required reinforcing steel (and, for concrete foundations, the required forms) are in place, with the foundation materials on the job. The one listed exception is ready-mixed concrete (ASTM C94), which does not need to be on the job when the inspection is made.

Keep studying

Read the Section 1 study notes: Planning and Estimating

All General Building topics

Test yourself

Try 25 free General Building practice questions from all five sections. Each answer explains the rule and names the code section it comes from. No sign-up.

See what the General Building exam covers