Skip to content
CalContractorPrep
Menu

CSLB General Building (B) practice questions: Shop drawings, plans, and specifications

Section 1 of 5: Planning and Estimating

4 free practice questions on shop drawings, plans, and specifications, part of a section that is about 15% of the General Building exam. Try each one, then open the answer: every choice is explained, and the answer names the code section or public rule it comes from.

Questions and answers

  1. 1. When a building permit is issued, the construction documents are approved by stamp. Under the California Building Code, where must the set returned to the applicant be kept?

    Planning and Estimating

    • A. At the work site, open to inspection by the building official
    • B. At the contractor's main office
    • C. With the owner's construction lender
    • D. With the architect until the final inspection
    Show answer

    Correct answer: A

    • A. At the work site, open to inspection by the building official

      Correct answer

      Correct: the approved set stays at the job site.

    • B. At the contractor's main office

      Wrong: the set must be at the work site, not the office.

    • C. With the owner's construction lender

      Wrong: the lender has no role in keeping the approved set.

    • D. With the architect until the final inspection

      Wrong: the set must be at the work site for the inspector.

    Explanation

    California Building Code section 107.3.1: when the permit is issued, the building official keeps one approved set, and the applicant gets the other set back. That set has to stay on the job site, where the building official can inspect it.

  2. 2. Under the California Building Code, how long must the building official keep one set of the approved construction documents?

    Planning and Estimating

    • A. At least 90 days after the permit is issued
    • B. At least 180 days after the permitted work is completed, or longer if state or local law requires
    • C. Until the certificate of occupancy is issued
    • D. At least 10 years after the permit is issued, in every case
    Show answer

    Correct answer: B

    • A. At least 90 days after the permit is issued

      Wrong: the period runs from completion of the work, not from permit issuance.

    • B. At least 180 days after the permitted work is completed, or longer if state or local law requires

      Correct answer

      Correct: 107.5 sets at least 180 days after completion, or longer where law requires.

    • C. Until the certificate of occupancy is issued

      Wrong: the documents must be kept after completion, for at least 180 days.

    • D. At least 10 years after the permit is issued, in every case

      Wrong: 107.5 sets 180 days; any longer period comes from other state or local law.

    Explanation

    California Building Code section 107.5 requires the building official to keep one set of approved construction documents for at least 180 days from the date the permitted work is completed, or for a longer period where state or local laws require.

  3. 3. Neither the construction documents for a new house nor the individual truss design drawings specify how the roof trusses are to be braced. Under California Residential Code section R802.10.3, how must the trusses be braced?

    Planning and Estimating

    • A. No bracing is needed once the roof sheathing is nailed
    • B. As the framing crew's foreman directs in the field
    • C. In accordance with accepted industry practice, such as the SBCA BCSI guide
    • D. Only as the building inspector specifies at the frame inspection
    Show answer

    Correct answer: C

    • A. No bracing is needed once the roof sheathing is nailed

      Wrong: R802.10.3 requires bracing against rotation and for lateral stability; it does not leave bracing out.

    • B. As the framing crew's foreman directs in the field

      Wrong: R802.10.3 points to accepted industry practice, not to a decision made in the field.

    • C. In accordance with accepted industry practice, such as the SBCA BCSI guide

      Correct answer

      Correct: with no bracing specified, R802.10.3 falls back to accepted industry practice such as BCSI.

    • D. Only as the building inspector specifies at the frame inspection

      Wrong: the inspector checks the work; R802.10.3 does not make the inspector specify the bracing.

    Explanation

    California Residential Code section R802.10.3 requires trusses to be braced against rotation and for lateral stability as the building's construction documents and the individual truss design drawings specify. Where neither gives specific bracing requirements, the trusses are braced following accepted industry practice; the section names the SBCA Building Component Safety Information (BCSI) guide as an example.

  4. 4. You are checking the toilet and lavatory clearances on a bathroom plan for a new house. The California Residential Code sends you to which code book for fixture spacing?

    Planning and Estimating

    • A. California Mechanical Code
    • B. California Electrical Code
    • C. California Energy Code
    • D. California Plumbing Code
    Show answer

    Correct answer: D

    • A. California Mechanical Code

      Wrong: the Mechanical Code covers HVAC and exhaust, not fixture spacing.

    • B. California Electrical Code

      Wrong: the Electrical Code covers wiring, not fixture spacing.

    • C. California Energy Code

      Wrong: the Energy Code covers energy efficiency, not fixture spacing.

    • D. California Plumbing Code

      Correct answer

      Correct: R327.1 refers fixture spacing to the California Plumbing Code.

    Explanation

    California Residential Code section R327.1 does not give toilet and bath fixture clearances itself; it refers fixture spacing to the California Plumbing Code.

Keep studying

Read the Section 1 study notes: Planning and Estimating

All General Building topics

Test yourself

Try 25 free General Building practice questions from all five sections. Each answer explains the rule and names the code section it comes from. No sign-up.

See what the General Building exam covers