  1. 1. A project is covered by the 2022 Construction Stormwater General Permit. What site-specific plan does the permit require?

    Safety

    • A. A Stormwater Pollution Prevention Plan (SWPPP)
    • B. A Spill Containment Plan filed with the fire department
    • C. A Health and Safety Plan for the crew
    • D. A Traffic Control Plan
    Show answer

    Correct answer: A

    • A. A Stormwater Pollution Prevention Plan (SWPPP)

      Correct answer

      Correct: a site-specific SWPPP.

    • B. A Spill Containment Plan filed with the fire department

      Wrong: not the plan the stormwater permit requires.

    • C. A Health and Safety Plan for the crew

      Wrong: a worker safety plan is not the stormwater plan.

    • D. A Traffic Control Plan

      Wrong: traffic control is unrelated to stormwater coverage.

    Explanation

    The State Water Board's 2022 Construction Stormwater General Permit (Order 2022-0057-DWQ, in effect since September 1, 2023) requires a site-specific Stormwater Pollution Prevention Plan (SWPPP), developed and implemented by certified stormwater professionals (a Qualified SWPPP Developer and a Qualified SWPPP Practitioner).

    Source

  2. 2. A certified renovation firm finished a lead-safe job on a 1970 house. Under the federal rule, how long must it keep the records showing it followed the rule?

    Safety

    • A. 1 year after the renovation is completed
    • B. 3 years after the renovation is completed
    • C. 5 years after the renovation is completed
    • D. 10 years after the renovation is completed
    Show answer

    Correct answer: B

    • A. 1 year after the renovation is completed

      Wrong: too short.

    • B. 3 years after the renovation is completed

      Correct answer

      Correct: 3 years (40 CFR 745.86).

    • C. 5 years after the renovation is completed

      Wrong: 5 years is the firm certification and renovator refresher period, not record retention.

    • D. 10 years after the renovation is completed

      Wrong: too long.

    Explanation

    40 CFR 745.86 requires firms performing renovations to keep records that show compliance for 3 years after the renovation is completed.

    Source

  3. 3. During a renovation of a pre-1978 house, which paint removal method is prohibited by the federal lead renovation rule?

    Safety

    • A. Wet scraping by hand
    • B. Using a heat gun below 1,100 degrees Fahrenheit
    • C. Open-flame burning or torching of painted surfaces
    • D. Using a power sander with a shroud and HEPA vacuum attachment
    Show answer

    Correct answer: C

    • A. Wet scraping by hand

      Wrong: hand scraping is not on the prohibited list.

    • B. Using a heat gun below 1,100 degrees Fahrenheit

      Wrong: heat guns are allowed below 1,100 degrees F.

    • C. Open-flame burning or torching of painted surfaces

      Correct answer

      Correct: open-flame burning or torching is prohibited (40 CFR 745.85).

    • D. Using a power sander with a shroud and HEPA vacuum attachment

      Wrong: allowed when shrouded with a HEPA attachment.

    Explanation

    40 CFR 745.85 prohibits open-flame burning or torching of painted surfaces. Power sanders and grinders are allowed only with a shroud and HEPA vacuum attachment, and heat guns only below 1,100 degrees Fahrenheit.

  4. 4. A project needs coverage under the 2022 Construction Stormwater General Permit. When may construction activity begin?

    Safety

    • A. As soon as the SWPPP is written, before anything is filed
    • B. After the Notice of Intent is mailed to the local building department
    • C. After the first wet-season inspection
    • D. Once SMARTS has issued the project's WDID number
    Show answer

    Correct answer: D

    • A. As soon as the SWPPP is written, before anything is filed

      Wrong: the SWPPP is one of the documents that must be submitted; writing it does not give coverage.

    • B. After the Notice of Intent is mailed to the local building department

      Wrong: the Permit Registration Documents go to the State Water Board through SMARTS, not to the building department.

    • C. After the first wet-season inspection

      Wrong: coverage is needed before construction starts, not after an inspection.

    • D. Once SMARTS has issued the project's WDID number

      Correct answer

      Correct: construction may begin on receipt of the WDID number from SMARTS (Order section III.A).

    Explanation

    Order 2022-0057-DWQ section III.A requires the discharger to obtain a Waste Discharge Identification (WDID) number before construction starts, by certifying and submitting the Permit Registration Documents (Notice of Intent, site maps, SWPPP and fee) in the State Water Board's SMARTS system. Coverage starts, and construction may begin, when SMARTS issues the WDID. The WDID must be posted where the public can see it, or be available on request.

    Source

Keep studying

Read the Section 5 study notes: Safety

All General Building topics

Study guides for this section

Test yourself

Try 25 free General Building practice questions from all five sections. Each answer explains the rule and names the code section it comes from. No sign-up.

See what the General Building exam covers