Civil Code section 8414
Text as of October 25, 2026.
A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times:
(a) After the claimant ceases to provide work.
(b) Before the earlier of the following times:
(1) Ninety days after completion of the work of improvement.
(2) Thirty days after the owner records a notice of completion or cessation.
This is the law as we saved it on October 25, 2026. Laws change, so check the official site for the current wording. This page is for study only and is not legal advice.