Source text
Civil Code section 8412
Text as of October 25, 2026.
A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times:
(a) Ninety days after completion of the work of improvement.
(b) Sixty days after the owner records a notice
of completion or cessation.
This is the law as we saved it on October 25, 2026. Laws change, so check the official site for the current wording. This page is for study only and is not legal advice.