Skip to content
CalContractorPrep
Menu

Free practice quiz

25 questions from this exam section. You see the answer and a plain-English explanation with its source right after each one. Skipped questions count as incorrect. Each new quiz draws 25 questions at random from the 316 in this section.

Choose a section

Question 8 of 25

0 of 25 answered

Section: Contract Requirements and Execution

Contract Requirements and Execution
A city hires a contractor to build a $500,000 public library. The contract is not financed by revenue bonds. A magnitude 5.5 earthquake causes $15,000 of damage to work built to the plans and building standards. The contract makes the contractor pay for repairs. What is the most the contractor can be made to pay?