Question 1 of 25

0 of 25 answered

Section: Contract Requirements and Execution

Contract Requirements and Execution
A prime contractor claims it listed the wrong subcontractor in its public works bid because of a clerical error. It gives proper notice to the listed subcontractor. Under Public Contract Code section 4107.5, how long from the bid opening does the listed subcontractor have to file a written objection?