Question 20 of 25

0 of 25 answered

Section: Contract Requirements and Execution

Contract Requirements and Execution
A general contractor has a city public works contract. Its subcontract says the subcontractor's only remedy for a delay is more time. The general contractor then causes an unreasonable delay that nobody expected. Under Public Contract Code section 7102, may the subcontractor recover delay damages?