Skip to content
CalContractorPrep
Menu

Free practice quiz

25 questions from this exam section. You see the answer and a plain-English explanation with its source right after each one. Skipped questions count as incorrect. Each new quiz draws 25 questions at random from the 227 in this section.

Choose a section

Question 16 of 25

0 of 25 answered

Section: Business Finances

Business Finances
A customer's $350 check to a contractor is returned for insufficient funds. The contractor mails a written demand that meets all the rules of Civil Code section 1719. Within 30 days, the customer pays only $50 toward the check. There is no good faith dispute. How much does the customer now owe in total (the unpaid check amount plus damages)?