A supplier sold materials to a subcontractor on a public works job. It did not give the preliminary notice (early written notice) that the law requires. Later a notice of completion was recorded. Under Civil Code section 9560, it can still claim on the payment bond. It must give written notice to the surety and the bond principal (the contractor that gave the bond). How soon after the notice of completion was recorded must it give this notice?