Section: Contract Requirements and Execution

Contract Requirements and Execution
On a local public works job, the contractor digs an excavation deeper than four feet. The agency investigates and finds the underground conditions differ materially from the bid information. The conditions increase the contractor's cost. Under Public Contract Code section 7104, what must the agency do?