Question 10 of 25

0 of 25 answered

Section: Public Works

Public Works
A subcontractor on a school district project was not paid. It gave every required preliminary notice on time. It did not give the district a stop payment notice. It is still within the time limit to sue. Under Civil Code section 9564, can it still sue to enforce the payment bond?